    Pajares Tunnels, León-Asturias High-Speed Rail Line

    Construction for this tunnel took place between 2004 and 2009. The project consisted of the construction of twin tunnels with a diameter of 8.5 m and a length of 10.67 km.  The project was completed in March 2009.

    7.67 km were excavated using tunnel boring machines, and the remaining 3 km using conventional methods.

    General Information

    Location
    León - Asturias, Spain
    Contract type
    Construction
    Infrastructure
    Construction of twin tunnels with a diameter of 8.5 m and a length of 10.67 km, of which 7.67 km were excavated using tunnel boring machines, and 3 km using conventional methods
    Year of project completion
    2009

    Image Gallery

    discover other flagship projects

    Legacy Way Tunnel

    Brisbane, QLD (Australia)

    ACCIONA Infrastructure was lead partner of the Transcity Joint Venture, for the design, construction, operate and 10 year maintenance of the $1.5 billion Legacy Way project, in Brisbane, Queensland.

    Sydney Light Rail

    Sydney (Australia)

    ACCIONA Infrastructure is the Principal Design and Construct JV partner of the ALTRAC consortium, awarded with the contract to design and construct the $2.1 billion Sydney CBD South East Light Rail.

    Move up